In q-17 , please explain point no B.
Share
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
Hi,
Option B basically means that when there are Independent projects, you can either select two or more projects or altogether reject all depending upon the sign of NPV & whether IRR > Kc. Whenever NPV is positive, it basically means IRR >Kc, so we can accept the project.
A conflict arises between NPV & IRR when there are mutually exclusive projects i.e. when we can select only 1 project and we have to reject the other. Because in this case we have to see whose NPV is higher.
Hope this helps!