Why do we require Return less than KC if project is less risky? Won’t this project be a wealth destroyer if get return less than KC?
Share
Please briefly explain why you feel this question should be reported.
Please briefly explain why you feel this answer should be reported.
Please briefly explain why you feel this user should be reported.
Return here means Re. It doesn’t mean IRR. We compare IRR with Kc.
Re is what shareholder require. If the risk is high they demand more return (more Re). If the risk in the project is less, they require less return. (less Re)
Hope it helps