What will be the answer of 4.1(c)? Will it be risk defined or risk managed? I chose risk defined because in ICAI mat it is given that where risk strategy and policy is in place and is communicated and also risk appetite is defined, it is risk defined, but answer is given as risk managed …..
Share
Please listen audio for your query.
Thank you Sir